Pembangunan Tanggul Laut Muara Baru Capai 59 Persen

Muara Baru Embankment Construction Has Reached 59 Percent

Muara Baru Embankment Package 1 Construction, Penjaringan, North Jakarta has reached 59 percent. It has 2.3 kilometers long and is targeted will be finished in 2018.

Recently, embankment construction has been realized around 1.4 kilometers or about 59 percent

Ciliwung-Cisadane Flood Control Office (BBWSCC)'s National Capital Integrated Coastal Development (NCICD) Specific Non-Vertical Working Unit Head, Sudarto said, Muara Baru Embankment has a high elevation around 4.8 meters above sea level. This embankment is located along the coastal as long as 2.3 kilometers with width around 1 meter.

"Recently, embankment construction has been realized around 1.4 kilometers or about 59 percent. We are targeting this project to finish in 2018," he said when monitoring Muara Baru Embankment, North Jakarta.

Acting Governor to Visit NCICD Phase A Construction

He mentioned that this project is in package 1. While for package 2 is located in Kali Baru area, Cilincing.

Embankment is constructed in order to prevent coastal flooding to occur, because of land subsidence. Besides, sea water can rise due to sea and estuary embankment strengthening and elevation and also Jakarta northern coastal areas arrangement.

"It is built as a clear boundary for land development in coastal areas and it can prevent economy loss due to coastal flood," he closed.

Linked News
Popular News indeks
  1. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye1144 personFakhrizal Fakhri
  2. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye995 personAldi Geri Lumban Tobing
  3. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye952 personAldi Geri Lumban Tobing
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye728 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye628 personAnita Karyati